No | Uraian | Satuan | Koefisien | |
A | TENAGA | |||
1 | Pekerja | OH | 1.200 | |
2 | Tukang batu | OH | 0.200 | |
3 | Kepala tukang | OH | 0.020 | |
4 | Mandor | OH | 0.060 | |
B | BAHAN | |||
1 | Semen Portland | kg | 230 | |
2 | Pasir beton | kg | 893 | |
3 | Kerikil (Maks 30 mm) | kg | 1027 | |
4 | Air | Liter | 200 |
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) (K100) cm, w/c = 0,87