Uraian | Satuan | Koefisien | ||
TENAGA | ||||
Pekerja | OH | 0.800 | ||
Tukang | OH | 0.400 | ||
Kepala Tukang | OH | 0.040 | ||
BAHAN | ||||
Kapur Padam | m3 | 0.135 | ||
Pasir Pasang | m3 | 0.400 | ||
Tanah Liat | m3 | 0.948 |
Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL
Tags:
Uraian | Satuan | Koefisien | ||
TENAGA | ||||
Pekerja | OH | 0.800 | ||
Tukang | OH | 0.400 | ||
Kepala Tukang | OH | 0.040 | ||
BAHAN | ||||
Kapur Padam | m3 | 0.135 | ||
Pasir Pasang | m3 | 0.400 | ||
Tanah Liat | m3 | 0.948 |