No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 1,200 | 88.193,60 | 105.832,32 | |
Mandor | L.04 | OH | 0,045 | 137.609,12 | 6.192,41 | |
JUMLAH TENAGA KERJA | 112.024,73 | |||||
B | BAHAN | |||||
JUMLAH HARGA BAHAN | ||||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 112.024,73 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 11.202,47 | |||
F | Harga Satuan Pekerjaan (D+E) | 123.227,20 |
A.2.3.1.6. Menggali 1 m3 tanah lumpur sedalam 1 m