NO. | URAIAN PEKERJAAN | VOLUME | SAT | HARGA SATUAN (RP) | JUMLAH HARGA (RP) |
1 | Mobilisasi | 1,00 | ls | Rp 1.500.000,00 | Rp 1.500.000,00 |
2 | Papan Nama | 1,00 | Ls | Rp 650.000,00 | Rp 650.000,00 |
3 | Keselamatan dan Kesehatan Kerja | 1,00 | Ls | Rp 1.000.000,00 | Rp 1.000.000,00 |
4 | Galian Biasa | 35,25 | M3 | Rp 71.527,50 | Rp 2.521.344,38 |
5 | Timbunan Pilihan dari sumber galian | 61,68 | M3 | Rp 222.615,00 | Rp 13.730.893,20 |
6 | Beton strukur, fc20 MPa | 43,70 | M3 | Rp 848.404,28 | Rp 37.075.267,14 |
7 | Baja Tulangan Polos-BjTP 280 | 2.206,39 | Kg | Rp 12.396,83 | Rp 27.352.230,71 |
8 | Fondasi Cerucuk, Penyediaan dan Pemancangan | 367,50 | M3 | Rp 122.496,00 | Rp 45.017.280,00 |
9 | Pasangan Batu | 43,24 | M3 | Rp 844.203,00 | Rp 36.503.337,72 |
10 | Pipa Drainase PVC diameter 125 mm | 31,20 | M1 | Rp 139.483,98 | Rp 4.351.900,18 |
11 | Pipa Drainase PVC diameter 60 mm | 39,00 | M1 | Rp 51.373,32 | Rp 2.003.559,48 |
JUMLAH | Rp 171.705.812,80 |