| Uraian | Satuan | Koefisien | |
| TENAGA | |||
| Pekerja | OH | 0.297 | |
| Tukang batu | OH | 0.033 | |
| Tukang kayu | OH | 0.033 | |
| Tukang besi | OH | 0.033 | |
| Kepala tukang | OH | 0.01 | |
| Mandor | OH | 0.015 | |
| JUMLAH TENAGA KERJA | |||
| BAHAN | |||
| Kayu kelas III | m3 | 0.003 | |
| Paku 5 cm – 12 cm | kg | 0.02 | |
| Minyak bekisting | Liter | 0.20 | |
| Besi beton polos | kg | 3.600 | |
| Kawat beton | kg | 0.05 | |
| Semen Portland | kg | 5.500 | |
| Pasir beton | m3 | 0.009 | |
| Kerikil | m3 | 0.015 |