No | Uraian | Satuan | Koefisien | |
A | TENAGA | |||
1 | Pekerja | OH | 1.650 | |
2 | Tukang batu | OH | 0.275 | |
3 | Kepala tukang | OH | 0.028 | |
4 | Mandor | OH | 0.083 | |
B | BAHAN | |||
1 | Semen Portland | kg | 371 | |
2 | Pasir beton | kg | 698 | |
3 | Kerikil (Maks 30 mm) | kg | 1047 | |
4 | Air | Liter | 215 |