No | Uraian | Satuan | Koefisien | |
A | TENAGA | |||
1 | Pekerja | OH | 2.100 | |
2 | Tukang batu | OH | 0.35 | |
3 | Kepala tukang | OH | 0.035 | |
4 | Mandor | OH | 0.105 | |
B | BAHAN | |||
1 | Semen Portland | kg | 439 | |
2 | Pasir beton | kg | 670 | |
3 | Kerikil (Maks 30 mm) | kg | 1006 | |
4 | Air | Liter | 215 |