No | Uraian | Satuan | Koefisien | |
A | TENAGA | |||
1 | Pekerja | OH | 1.650 | |
2 | Tukang batu | OH | 0.275 | |
3 | Kepala tukang | OH | 0.028 | |
4 | Mandor | OH | 0.083 | |
B | BAHAN | |||
1 | PC/Portland Cement | kg | 276 | |
2 | Pasir Beton | kg | 828 | |
3 | Krikil | kg | 1012 | |
4 | Air | Liter | 215 |
Membuat 1 m3 beton mutu f’c = 9,8 Mpa (K125)
Tags: