Uraian | Satuan | Koefisien | |
TENAGA | |||
Pekerja | OH | 1.500 | |
Tukang batu | OH | 0.750 | |
Kepala tukang | OH | 0.075 | |
Mandor | OH | 0.075 | |
BAHAN | |||
Batu belah | m3 | 1.200 | |
Semen Portland | Kg | 41.000 | |
Kapur | m3 | 0.131 | |
Pasir pasang | m3 | 0.523 |
Pemasangan 1 m3 pondasi batu belah campuran ¼ SP : 1 KP : 4PP
Tags: