Harga | Jumlah | |||||
No | Uraian | Kode | Satuan | Koefisien | Satuan | Harga |
(Rp) | (Rp) | |||||
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,375 | 88.193,60 | 33.072,60 | |
Tukang | L.02 | OH | 0,125 | 123.490,40 | 15.436,300 | |
Kepala tukang | L.03 | OH | 0,012 | 130.549,76 | 1.566,597 | |
Mandor | L.04 | OH | 0,019 | 137.609,12 | 2.614,57 | |
JUMLAH TENAGA KERJA | 52.690,07 | |||||
B | BAHAN | |||||
Panel beton pracetak | Lbr | 0,986 | 183.430,00 | 180.861,98 | ||
Kolom beton pracetak | Batang | 0,525 | 406.368,00 | 213.343,20 | ||
Semen PC | Kg | 45,000 | 1.240,00 | 55.800,00 | ||
Pasir beton | m3 | 0,074 | 289.255,00 | 21.404,87 | ||
Koral | m3 | 0,146 | 216.353,33 | 31.587,59 | ||
JUMLAH HARGA BAHAN | 502.997,64 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 555.687,71 | ||||
E | Overhead & Profit (Contoh 10%) | 10% x D (maksimum) | 55.568,77 | |||
F | Harga Satuan Pekerjaan (D+E) | 611.256,48 |
A. 2.2.1.18. Pemasangan 1 m2 panel beton pracetak 5x50x213 cm