No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,300 | 88.193,60 | 26.458,08 | |
Mandor | L.04 | OH | 0,010 | 137.609,12 | 1.376,09 | |
JUMLAH TENAGA KERJA | 27.834,17 | |||||
B | BAHAN | |||||
Pasir urug | 1,200 | 85.000,00 | 102.000,00 | |||
JUMLAH HARGA BAHAN | 102.000,00 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 129.834,17 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 12.983,42 | |||
F | Harga Satuan Pekerjaan (D+E) | 142.817,59 |
A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug
Tags: