No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,800 | 88.193,60 | 70.554,880 | |
Tukang | L.02 | OH | 0,400 | 123.490,40 | 49.396,160 | |
Kepala Tukang | L.03 | OH | 0,040 | 130.549,76 | 5.221,990 | |
Mandor | L.04 | OH | 0,080 | 137.609,12 | 11.008,730 | |
JUMLAH TENAGA KERJA | 136.181,76 | |||||
B | BAHAN | |||||
Kapur Padam | m3 | 0,135 | 82.300,00 | 11.110,500 | ||
Pasir Pasang | m3 | 0,400 | 227641,337 | 91.056,535 | ||
Tanah Liat | m3 | 0,948 | 76723,125 | 72.733,523 | ||
JUMLAH HARGA BAHAN | 174.900,56 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 311.082,32 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 31.108,23 | |||
F | Harga Satuan Pekerjaan (D+E) | 342.190,55 |