No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,500 | 88.193,60 | 44.096,80 | |
Mandor | L.04 | OH | 0,050 | 137.609,12 | 6.880,46 | |
JUMLAH TENAGA KERJA | 50.977,26 | |||||
B | BAHAN | |||||
JUMLAH HARGA BAHAN | ||||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 50.977,26 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 5.097,73 | |||
F | Harga Satuan Pekerjaan (D+E) | 56.074,98 |
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Tags: