No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
1 | Pekerja | L.01 | OH | 1,650 | 88.193,60 | 145.519,440 |
2 | Tukang batu | L.02 | OH | 0,275 | 116.431,04 | 32.018,536 |
3 | Kepala tukang | L.03 | OH | 0,028 | 130.549,76 | 3.655,393 |
4 | Mandor | L.04 | OH | 0,083 | 137.609,12 | 11.421,557 |
JUMLAH TENAGA KERJA | 192.614,926 | |||||
B | BAHAN | |||||
1 | Semen portland | kg | 299 | 1.240,00 | 370.760,000 | |
2 | Pasir beton | kg | 799 | 206,61 | 165.081,961 | |
3 | Kerikil (Maks 30 mm) | kg | 1017 | 193,75 | 197.044,974 | |
4 | Air | Liter | 215 | 200,00 | 43.000,000 | |
JUMLAH HARGA BAHAN | 775.886,935 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 968.501,861 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 96.850,186 | |||
F | Harga Satuan Pekerjaan (D+E) | 1.065.352,047 |
A.4.1.1.3 Membuat 1 m3 beton mutu f’c = 12,2 Mpa (K150)
Tags: