| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
| A | TENAGA | |||||
| Pekerja | L.01 | OH | 0,025 | 88.193,60 | 2.204,84 | |
| Tukang besi | L.02 | OH | 0,025 | 116.431,04 | 2.910,78 | |
| Kepala tukang | L.03 | OH | 0,025 | 130.549,76 | 3.263,74 | |
| Mandor | L.04 | OH | 0,001 | 137.609,12 | 137,61 | |
| JUMLAH TENAGA KERJA | 8.516,97 | |||||
| B | BAHAN | |||||
| Jaring kawat baja dilas | kg | 10,2 | 100.498,48 | 1.025.084,45 | ||
| Kawat beton | kg | 0,050 | 21.165,00 | 1.058,25 | ||
| JUMLAH HARGA BAHAN | 1.026.142,70 | |||||
| C | PERALATAN | |||||
| JUMLAH HARGA ALAT | ||||||
| D | Jumlah (A+B+C) | 1.034.659,66 | ||||
| E | Overhead & Profit 10 % | 10% x D (maksimum) | 103.465,97 | |||
| F | Harga Satuan Pekerjaan (D+E) | 1.138.125,63 | ||||
| G | Harga Satuan pembesian 1 kg | 113.812,56 | ||||