No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,025 | 88.193,60 | 2.204,84 | |
Tukang besi | L.02 | OH | 0,025 | 116.431,04 | 2.910,78 | |
Kepala tukang | L.03 | OH | 0,025 | 130.549,76 | 3.263,74 | |
Mandor | L.04 | OH | 0,001 | 137.609,12 | 137,61 | |
JUMLAH TENAGA KERJA | 8.516,97 | |||||
B | BAHAN | |||||
Jaring kawat baja dilas | kg | 10,2 | 100.498,48 | 1.025.084,45 | ||
Kawat beton | kg | 0,050 | 21.165,00 | 1.058,25 | ||
JUMLAH HARGA BAHAN | 1.026.142,70 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 1.034.659,66 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 103.465,97 | |||
F | Harga Satuan Pekerjaan (D+E) | 1.138.125,63 | ||||
G | Harga Satuan pembesian 1 kg | 113.812,56 |
A.4.1.1.19 Pemasangan 10 kg jaring kawat baja (wiremesh)