| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
| A | TENAGA | |||||
| Pekerja | L.01 | OH | 0,050 | 88.193,60 | 4.409,68 | |
| Tukang besi | L.02 | OH | 0,050 | 116.431,04 | 5.821,55 | |
| Kepala tukang | L.03 | OH | 0,005 | 130.549,76 | 652,75 | |
| Mandor | L.04 | OH | 0,003 | 137.609,12 | 412,83 | |
| JUMLAH TENAGA KERJA | 11.296,81 | |||||
| B | BAHAN | |||||
| Besi beton (polos/ulir) | kg | 10,500 | 12.000,00 | 126.000,00 | ||
| Kawat beton | kg | 0,100 | 21.165,00 | 2.116,50 | ||
| JUMLAH HARGA BAHAN | 128.116,50 | |||||
| C | PERALATAN | |||||
| JUMLAH HARGA ALAT | ||||||
| D | Jumlah (A+B+C) | 139.413,31 | ||||
| E | Overhead & Profit 10 % | 10% x D (maksimum) | 13.941,33 | |||
| F | Harga Satuan Pekerjaan (D+E) | 153.354,64 | ||||
| G | Harga Satuan pembesian 1 kg | 15.335,46 | ||||