No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,520 | 88.193,60 | 45.860,67 | |
Tukang kayu | L.02 | OH | 0,260 | 123.490,40 | 32.107,50 | |
Kepala tukang | L.03 | OH | 0,026 | 130.549,76 | 3.394,29 | |
Mandor | L.04 | OH | 0,026 | 137.609,12 | 3.577,84 | |
JUMLAH TENAGA KERJA | 84.940,31 | |||||
B | BAHAN | |||||
Kayu kelas III | m3 | 0,045 | 1.500.000,00 | 67.500,00 | ||
Paku 5 cm – 10 cm | kg | 0,300 | 21.870,50 | 6.561,15 | ||
Minyak bekisting | Liter | 0,100 | 19.500,00 | 1.950,00 | ||
JUMLAH HARGA BAHAN | 76.011,15 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 160.951,46 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 16.095,15 | |||
F | Harga Satuan Pekerjaan (D+E) | 177.046,60 |
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof/kolom praktis/ring balk
Tags: