| No | Uraian | Satuan | Koefisien | |
| A | TENAGA | |||
| 1 | Pekerja | OH | 2.100 | |
| 2 | Tukang batu | OH | 0.35 | |
| 3 | Kepala tukang | OH | 0.035 | |
| 4 | Mandor | OH | 0.105 | |
| B | BAHAN | |||
| 1 | Semen Portland | kg | 400 | |
| 2 | Pasir beton | m3 | 0.480 | |
| 3 | Kerikil (2cm/3cm) | m3 | 0.800 | |
| 4 | Strorox – 100 | kg | 1.200 |