Uraian | Satuan | Koefisien | |
TENAGA | |||
Pekerja | OH | 3.400 | |
Tukang batu | OH | 0.850 | |
Kepala tukang | OH | 0.085 | |
Mandor | OH | 0.17 | |
BAHAN | |||
Batu belah | m3 | 0.480 | |
Semen Portland | Kg | 194.000 | |
Pasir beton | m3 | 0.312 | |
Kerikil | m3 | 0.468 | |
Besi beton | Kg | 126.000 | |
Kawat beton | Kg | 1.800 |
Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB: 3 Kr dan 40% batu belah