| Harga | Jumlah | |||||
| No | Uraian | Kode | Satuan | Koefisien | Satuan | Harga |
| (Rp) | (Rp) | |||||
| A | TENAGA | |||||
| Tukang kayu | L.02 | OH | 0,300 | 123.490,40 | 37.047,120 | |
| Kepala tukang | L.03 | OH | 0,030 | 130.549,76 | 3.916,493 | |
| JUMLAH TENAGA KERJA | 40.963,613 | |||||
| B | BAHAN | |||||
| Kayu papan kelas III | m3 | 0,360 | 1.500.000,00 | 540.000,000 | ||
| Kayu balok 5/7 kelas III | m3 | 0,360 | 1.500.000,00 | 540.000,000 | ||
| Paku biasa | kg | 0,080 | 15.000,00 | 1.200,000 | ||
| JUMLAH HARGA BAHAN | 1.081.200,000 | |||||
| C | PERALATAN | |||||
| JUMLAH HARGA ALAT | ||||||
| D | Jumlah (A+B+C) | 1.122.163,613 | ||||
| E | Overhead & Profit 10 % | 10% x D (maksimum) | 112.216,361 | |||
| F | Harga Satuan Pekerjaan (D+E) | 1.234.379,974 | ||||