Harga | Jumlah | |||||
No | Uraian | Kode | Satuan | Koefisien | Satuan | Harga |
(Rp) | (Rp) | |||||
A | TENAGA | |||||
Pekerja | L.01 | OH | 13,334 | 88.193,60 | 1.175.973,462 | |
Mandor | L.04 | OH | 0,666 | 137.609,12 | 91.647,674 | |
JUMLAH TENAGA KERJA | 1.267.621,136 | |||||
B | BAHAN | |||||
JUMLAH HARGA BAHAN | ||||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 1.267.621,136 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 126.762,114 | |||
F | Harga Satuan Pekerjaan (D+E) | 1.394.383,250 |
A. 2.2.1.13. Pembongkaran 1 m3 beton bertulang
Tags: