No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 0,250 | 88.193,60 | 22.048,40 | |
Mandor | L.04 | OH | 0,025 | 137.609,12 | 3.440,23 | |
JUMLAH TENAGA KERJA | 25.488,63 | |||||
B | BAHAN | |||||
Sirtu | m3 | 1,200 | 85.000,00 | 102.000,00 | ||
JUMLAH HARGA BAHAN | 102.000,00 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 127.488,63 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 12.748,86 | |||
F | Harga Satuan Pekerjaan (D+E) | 140.237,49 |
A.2.3.1.14. Pengurugan 1 m3 sirtu padat
Tags: