| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
| A | TENAGA | |||||
| Pekerja | L.01 | OH | 0,250 | 88.193,60 | 22.048,40 | |
| Mandor | L.04 | OH | 0,025 | 137.609,12 | 3.440,23 | |
| JUMLAH TENAGA KERJA | 25.488,63 | |||||
| B | BAHAN | |||||
| Sirtu | m3 | 1,200 | 85.000,00 | 102.000,00 | ||
| JUMLAH HARGA BAHAN | 102.000,00 | |||||
| C | PERALATAN | |||||
| JUMLAH HARGA ALAT | ||||||
| D | Jumlah (A+B+C) | 127.488,63 | ||||
| E | Overhead & Profit 10 % | 10% x D (maksimum) | 12.748,86 | |||
| F | Harga Satuan Pekerjaan (D+E) | 140.237,49 | ||||