No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
A | TENAGA | |||||
Pekerja | L.01 | OH | 2,100 | 88.193,60 | 185.206,56 | |
Tukang batu | L.02 | OH | 0,35 | 116.431,04 | 40.750,86 | |
Kepala tukang | L.03 | OH | 0,035 | 130.549,76 | 4.569,24 | |
Mandor | L.04 | OH | 0,105 | 137.609,12 | 14.448,96 | |
JUMLAH TENAGA KERJA | 244.975,62 | |||||
B | BAHAN | |||||
Semen Portland | kg | 400 | 1.240,00 | 496.000,00 | ||
Pasir beton | m3 | 0,480 | 206,61 | 99,17 | ||
Kerikil (2cm/3cm) | m3 | 0,800 | 193,75 | 155,00 | ||
Strorox – 100 | kg | 1,200 | 38.500,00 | 46.200,00 | ||
JUMLAH HARGA BAHAN | 542.454,17 | |||||
C | PERALATAN | |||||
JUMLAH HARGA ALAT | ||||||
D | Jumlah (A+B+C) | 787.429,80 | ||||
E | Overhead & Profit 10 % | 10% x D (maksimum) | 78.742,98 | |||
F | Harga Satuan Pekerjaan (D+E) | 866.172,78 |
A.4.1.1.13 Membuat 1 m3 beton kedap air dengan strorox – 100