| No | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) | Jumlah Harga (Rp) |
| A | TENAGA | |||||
| Pekerja | L.01 | OH | 0,070 | 88.193,60 | 6.173,55 | |
| Tukang besi | L.02 | OH | 0,070 | 116.431,04 | 8.150,17 | |
| Kepala tukang | L.03 | OH | 0,007 | 130.549,76 | 913,85 | |
| Mandor | L.04 | OH | 0,004 | 137.609,12 | 550,44 | |
| JUMLAH TENAGA KERJA | 15.788,01 | |||||
| B | BAHAN | |||||
| Besi beton ulir | kg | 10,500 | 12.000,00 | 126.000,00 | ||
| Kawat beton | kg | 0,150 | 21.165,00 | 3.174,75 | ||
| JUMLAH HARGA BAHAN | 129.174,75 | |||||
| C | PERALATAN | |||||
| JUMLAH HARGA ALAT | ||||||
| D | Jumlah (A+B+C) | 144.962,76 | ||||
| E | Overhead & Profit 10 % | 10% x D (maksimum) | 14.496,28 | |||
| F | Harga Satuan Pekerjaan (D+E) | 159.459,04 | ||||
| G | Harga Satuan pembesian 1 kg dengan besi ulir | 15.945,90 | ||||